Production Order Confirmation in SAP (CO11N)

Complete Step-by-Step Guide – Discrete Manufacturing

Overview

Production Order Confirmation is used to record the actual execution of a production order (operations completed, quantities produced, activities consumed, and goods movements). The most commonly used transaction is CO11N (Time Ticket Confirmation).

Prerequisites

  • Production Order is created and Released (CO01)
  • Components are available (or backflush is active)
  • Authorization for confirmation transactions
  • Understanding of the operations in the order

Step-by-Step Process (CO11N)

1

Enter Transaction Code

Go to transaction CO11N (Time Ticket for Production Order) and press Enter.

2

Enter Order & Operation

  • Enter the Production Order number
  • Enter the Operation number (or leave blank to select)
  • Press Enter
  • System displays operation details, standard values, and quantities
3

Enter Confirmation Data

  • Yield – Quantity of good material produced
  • Scrap – Quantity of scrap (if any)
  • Rework – Quantity to be reworked (if applicable)
  • Activity Times – Setup time, Machine time, Labor time, etc.
  • Personnel Number / Work Center (optional)
  • Posting Date – Date of confirmation
  • Select Final Confirmation if the operation is completely finished
4

Goods Movements

  • If Backflush is active → Components are automatically issued
  • If Auto GR is active on the last operation → Finished product is automatically received
  • Otherwise, go to the Goods Movements tab to post GI/GR manually
5

Save the Confirmation

Click the Save button (or press Ctrl + S).

The system:

  • Updates the Production Order with confirmed quantities
  • Posts goods movements (if applicable)
  • Updates costs and activity consumption
  • Changes the status of the operation/order

Quick Process Flow

CO11N → Enter Order + Operation → Enter Yield / Scrap / Activities → Save

Alternative Confirmation Transactions

T-Code Description When to Use
CO11N Time Ticket Confirmation Most common – recommended
CO15 Order Confirmation Confirm entire order at once
CO11 Time Ticket (Classic) Older version of CO11N
CO19 Progress Confirmation Progress-based confirmation
CO1F Fast Entry Confirmation Quick entry of multiple confirmations

Related Transaction Codes

T-Code Description
CO11N Time Ticket Confirmation
CO15 Production Order Confirmation
CO13 Cancel Confirmation
CO14 Display Confirmation
COOIS Production Order Information System
COGI Reprocess Goods Movement Errors
COFC Reprocess Confirmation Errors
MIGO Manual Goods Movement
CO88 Order Settlement
Important:
  • If goods movements fail during confirmation, they appear in COGI for reprocessing.
  • Final confirmation sets the operation status to CNF (Confirmed).
  • After all operations are confirmed and GR is done, the order can be settled using CO88.

Helpful Tips

  • Prefer CO11N – it is modern and user-friendly.
  • Always check the Yield quantity carefully – it drives Goods Receipt and costing.
  • Use “Final Confirmation” indicator when the operation is completely finished.
  • If components are not backflushed, post Goods Issue separately using MIGO.
  • You can cancel a confirmation using transaction CO13.
  • Monitor open confirmations and errors via COOIS and COGI.