Overview

A Production Order is used in discrete manufacturing to produce a material based on a Bill of Material (BOM) and Routing. It is the counterpart of the Process Order (COR1) used in process industries.

Prerequisites

  • Material Master exists (Finished / Semi-finished)
  • Bill of Material (BOM) is created (CS01)
  • Routing is created (CA01)
  • Production Version is maintained (recommended)
  • Work Centers are available
  • Authorization for transaction CO01

Step-by-Step Process

1

Enter Transaction Code

Go to transaction CO01 (Create Production Order) and press Enter.

2

Initial Screen

  • Material: Enter the material to be produced
  • Production Plant: Enter the plant
  • Order Type: Enter order type (commonly PP01 for standard production order)
  • Press Enter
3

Header – General Data

  • Total Quantity: Enter the order quantity
  • Order Start Date / Finish Date: Enter basic dates
  • Scheduling Type: Forward / Backward / Current date
  • Production Version: Select if multiple versions exist

Press Enter. The system explodes the BOM and Routing.

4

Review Operations

  • Go to the Operations tab
  • System copies operations from the Routing
  • Check Work Centers, Control Keys, and Standard Values
  • You can make limited changes if required
5

Review Components

  • Go to the Components tab
  • System copies components from the BOM
  • Check quantities, storage locations, and backflush indicators
  • You can add or change components if authorized
6

Additional Data (Optional)

  • Assignment tab → MRP Controller, Production Supervisor
  • Goods Receipt tab → Storage location for finished product
  • Control tab → Release, scheduling, and costing parameters
7

Release and Save

  • Click the Release button (status changes to REL)
  • Click Save
  • System generates a unique Production Order Number

Note down the order number for further processing.

Quick Process Flow

CO01 → Material + Plant + Order Type → Quantity + Dates → Review Operations & Components → Release → Save

Related Transaction Codes

T-Code Description
CO01 Create Production Order
CO02 Change Production Order
CO03 Display Production Order
CO11N Production Order Confirmation (Time Ticket)
CO15 Production Order Confirmation (Order level)
COOIS Production Order Information System
COHV Mass Processing of Production Orders
MIGO Goods Movement (GI / GR)
CO88 Order Settlement
Note: After creating and releasing the Production Order, the next typical steps are:
  • Goods Issue of components (MIGO or Backflush)
  • Confirmation of operations (CO11N / CO15)
  • Goods Receipt of finished product (MIGO)
  • Order Settlement (CO88)

Helpful Tips

  • Always check that a valid BOM and Routing exist before creating the order.
  • Use Order Type PP01 for standard production orders.
  • You can create a Production Order with reference to a Planned Order (from MRP).
  • Release the order immediately if you want to perform goods movements and confirmations.
  • Use COOIS to monitor production orders after creation.
  • For process industries, use COR1 instead of CO01.